New Client Implementation Schedule
Revision as of 19:19, 27 December 2018 by Abilotti (talk | contribs) (→Hardware / Software and GC training)
Pre Sale Engineering
- Client Personnel
- Day to day contacts
 - Finance
 - IT
 - Fleet
 - Mechanics
 - Safety
 - Pre Implementation Engineering w/Support
 
 
Client Locations (qty)
- Parking
- Facing the AP
 - Distance from PC to AP
 - From Vehicles to AP
 - frequency of Parking
 - vehicles power cut Off?
 - Types of vehicles
 - Number of vehicles per location
 - GSMs?
- Cellular Download
 - Tracking (Live Look In) only
 
 - Driver ID?
 - Facial Recognition
 
 
Camera Installation
- Client install
 - Idrive Install
 - Train the Trainer
 - Other?
 
Hardware Base Station / Access Point location
- Or Cellular only
 - Or Cellular and Access Point mixed
 - Multiple Access Points needed?
- Additional Hardware
- additional APs
 - cables
 - length of needed cables
 - multi-port switches
 - High Power PoE(s)
 - WiFi Bridges
 
 
 - Additional Hardware
 
- Base Station requirements
- Always ON Internet type
 - larger HDD
 - Terminal
- Download Point
 
 
 
- Access Point location
- Or Cellular only
 - Or Cellular and Access Point mixed
 - Multiple Access Points needed?
- Additional Hardware
- additional APs
 
 
 - Additional Hardware
 
 
After Sale Installation procedures
- Order of Installation
 
- Base Station and Internet connection (VPN For AP or PC access remote)
 - Idrive Support contacted and logged in to configure
 - Access Points(s) Installed and Configured
 
- Employee Introduction
 
- Vehicles
- Vehicle Availability
- plan on 45 min average install time (per installer)
 
 - Vehicle Nomenclature
- Weights
 
 - Driver Info (if needed)
 
 - Vehicle Availability
 
Hardware / Software and GC training
- Typically 1 week after first camera installation
- Review Client?
 - Notification to Review Dept... (30 day Notice)
 - GSM Activation and Provisioning